project

Design & Build of Upgrading Projects for G18G

DEVELOPER / MAIN CONTRACTOR

HDB

COMMENCEMENT DATE / COMPLETION DATE

Completed in September 2018

CONTRACT SUM (APPROXIMATELY)

-

project

Design & Build of Upgrading Projects for G18G

DEVELOPER / MAIN CONTRACTOR

  • Oxley Serangoon Pte Ltd
  • L.S Construction Pte Ltd

HDB

COMMENCEMENT DATE / COMPLETION DATE

Completed in September 2018

CONTRACT SUM (APPROXIMATELY)

-

project

Design & Build of Upgrading Projects for G18G

DEVELOPER / MAIN CONTRACTOR

-->
  • Oxley Serangoon Pte Ltd
  • L.S Construction Pte Ltd

HDB

COMMENCEMENT DATE / COMPLETION DATE

Completed in September 2018

CONTRACT SUM (APPROXIMATELY)

-

project

Design & Build of Upgrading Projects for G18G

DEVELOPER / MAIN CONTRACTOR

-->

HDB

COMMENCEMENT DATE / COMPLETION DATE

Completed in September 2018

CONTRACT SUM (APPROXIMATELY)

-

project

Design & Build of Upgrading Projects for G18G

DEVELOPER / MAIN CONTRACTOR

-->

HDB

COMMENCEMENT DATE / COMPLETION DATE

Completed in September 2018

CONTRACT SUM (APPROXIMATELY)

-

project

Design & Build of Upgrading Projects for G18G

DEVELOPER / MAIN CONTRACTOR

-->

HDB

COMMENCEMENT DATE / COMPLETION DATE

Completed in September 2018

CONTRACT SUM (APPROXIMATELY)

-

project

Design & Build of Upgrading Projects for G18G

DEVELOPER / MAIN CONTRACTOR

-->

HDB

COMMENCEMENT DATE / COMPLETION DATE

Completed in September 2018

CONTRACT SUM (APPROXIMATELY)

-

project

Design & Build of Upgrading Projects for G18G

DEVELOPER / MAIN CONTRACTOR

  • Oxley Serangoon Pte Ltd
  • L.S Construction Pte Ltd

HDB

COMMENCEMENT DATE / COMPLETION DATE

Completed in September 2018

CONTRACT SUM (APPROXIMATELY)

-

project

Design & Build of Upgrading Projects for G18G

DEVELOPER / MAIN CONTRACTOR

--> <

HDB

COMMENCEMENT DATE / COMPLETION DATE

Completed in September 2018

CONTRACT SUM (APPROXIMATELY)

-