Proposed Development of Changi East to Effect 3 Runway Operations at Singapore Changi Airport (Package One). Sub-contract works including following scope of works;
1. Supply, Installation and Construction of AFL Manhole including Draw Pits, Transformer Pits and AFL Duct works
2. Supply and Installation Airfield Lightning System Plinths and duct.
3. Supply and Installation of Fire Hydrant manholes including hunching of pipes.
4. Sub-soil System works including supply and installation of manholes.
5. Installation of Security Fence
6. Demolition of Existing Runway lights, drainage system and diversion of existing canal.
DEVELOPER / MAIN CONTRACTOR
Samsung-Koh Brothers JV
COMMENCEMENT DATE / COMPLETION DATE
May 2016 - Current
CONTRACT SUM (APPROXIMATELY)
-
project
Proposed Development of Changi East to Effect 3 Runway Operations at Singapore Changi Airport (Package One). Sub-contract works including following scope of works;
1. Supply, Installation and Construction of AFL Manhole including Draw Pits, Transformer Pits and AFL Duct works
2. Supply and Installation Airfield Lightning System Plinths and duct.
3. Supply and Installation of Fire Hydrant manholes including hunching of pipes.
4. Sub-soil System works including supply and installation of manholes.
5. Installation of Security Fence
6. Demolition of Existing Runway lights, drainage system and diversion of existing canal.
DEVELOPER / MAIN CONTRACTOR
- Oxley Serangoon Pte Ltd
- L.S Construction Pte Ltd
Samsung-Koh Brothers JV
COMMENCEMENT DATE / COMPLETION DATE
May 2016 - Current
CONTRACT SUM (APPROXIMATELY)
-
project
Proposed Development of Changi East to Effect 3 Runway Operations at Singapore Changi Airport (Package One). Sub-contract works including following scope of works;
1. Supply, Installation and Construction of AFL Manhole including Draw Pits, Transformer Pits and AFL Duct works
2. Supply and Installation Airfield Lightning System Plinths and duct.
3. Supply and Installation of Fire Hydrant manholes including hunching of pipes.
4. Sub-soil System works including supply and installation of manholes.
5. Installation of Security Fence
6. Demolition of Existing Runway lights, drainage system and diversion of existing canal.
DEVELOPER / MAIN CONTRACTOR
- Oxley Serangoon Pte Ltd
- L.S Construction Pte Ltd
Samsung-Koh Brothers JV
COMMENCEMENT DATE / COMPLETION DATE
May 2016 - Current
CONTRACT SUM (APPROXIMATELY)
-
project
Proposed Development of Changi East to Effect 3 Runway Operations at Singapore Changi Airport (Package One). Sub-contract works including following scope of works;
1. Supply, Installation and Construction of AFL Manhole including Draw Pits, Transformer Pits and AFL Duct works
2. Supply and Installation Airfield Lightning System Plinths and duct.
3. Supply and Installation of Fire Hydrant manholes including hunching of pipes.
4. Sub-soil System works including supply and installation of manholes.
5. Installation of Security Fence
6. Demolition of Existing Runway lights, drainage system and diversion of existing canal.
DEVELOPER / MAIN CONTRACTOR
Samsung-Koh Brothers JV
COMMENCEMENT DATE / COMPLETION DATE
May 2016 - Current
CONTRACT SUM (APPROXIMATELY)
-
project
Proposed Development of Changi East to Effect 3 Runway Operations at Singapore Changi Airport (Package One). Sub-contract works including following scope of works;
1. Supply, Installation and Construction of AFL Manhole including Draw Pits, Transformer Pits and AFL Duct works
2. Supply and Installation Airfield Lightning System Plinths and duct.
3. Supply and Installation of Fire Hydrant manholes including hunching of pipes.
4. Sub-soil System works including supply and installation of manholes.
5. Installation of Security Fence
6. Demolition of Existing Runway lights, drainage system and diversion of existing canal.
DEVELOPER / MAIN CONTRACTOR
Samsung-Koh Brothers JV
COMMENCEMENT DATE / COMPLETION DATE
May 2016 - Current
CONTRACT SUM (APPROXIMATELY)
-
project
Proposed Development of Changi East to Effect 3 Runway Operations at Singapore Changi Airport (Package One). Sub-contract works including following scope of works;
1. Supply, Installation and Construction of AFL Manhole including Draw Pits, Transformer Pits and AFL Duct works
2. Supply and Installation Airfield Lightning System Plinths and duct.
3. Supply and Installation of Fire Hydrant manholes including hunching of pipes.
4. Sub-soil System works including supply and installation of manholes.
5. Installation of Security Fence
6. Demolition of Existing Runway lights, drainage system and diversion of existing canal.
DEVELOPER / MAIN CONTRACTOR
Samsung-Koh Brothers JV
COMMENCEMENT DATE / COMPLETION DATE
May 2016 - Current
CONTRACT SUM (APPROXIMATELY)
-
project
Proposed Development of Changi East to Effect 3 Runway Operations at Singapore Changi Airport (Package One). Sub-contract works including following scope of works;
1. Supply, Installation and Construction of AFL Manhole including Draw Pits, Transformer Pits and AFL Duct works
2. Supply and Installation Airfield Lightning System Plinths and duct.
3. Supply and Installation of Fire Hydrant manholes including hunching of pipes.
4. Sub-soil System works including supply and installation of manholes.
5. Installation of Security Fence
6. Demolition of Existing Runway lights, drainage system and diversion of existing canal.
DEVELOPER / MAIN CONTRACTOR
Samsung-Koh Brothers JV
COMMENCEMENT DATE / COMPLETION DATE
May 2016 - Current
CONTRACT SUM (APPROXIMATELY)
-
project
Proposed Development of Changi East to Effect 3 Runway Operations at Singapore Changi Airport (Package One). Sub-contract works including following scope of works;
1. Supply, Installation and Construction of AFL Manhole including Draw Pits, Transformer Pits and AFL Duct works
2. Supply and Installation Airfield Lightning System Plinths and duct.
3. Supply and Installation of Fire Hydrant manholes including hunching of pipes.
4. Sub-soil System works including supply and installation of manholes.
5. Installation of Security Fence
6. Demolition of Existing Runway lights, drainage system and diversion of existing canal.
DEVELOPER / MAIN CONTRACTOR
- Oxley Serangoon Pte Ltd
- L.S Construction Pte Ltd
Samsung-Koh Brothers JV
COMMENCEMENT DATE / COMPLETION DATE
May 2016 - Current
CONTRACT SUM (APPROXIMATELY)
-
project
Proposed Development of Changi East to Effect 3 Runway Operations at Singapore Changi Airport (Package One). Sub-contract works including following scope of works;
1. Supply, Installation and Construction of AFL Manhole including Draw Pits, Transformer Pits and AFL Duct works
2. Supply and Installation Airfield Lightning System Plinths and duct.
3. Supply and Installation of Fire Hydrant manholes including hunching of pipes.
4. Sub-soil System works including supply and installation of manholes.
5. Installation of Security Fence
6. Demolition of Existing Runway lights, drainage system and diversion of existing canal.
DEVELOPER / MAIN CONTRACTOR
Samsung-Koh Brothers JV
COMMENCEMENT DATE / COMPLETION DATE
May 2016 - Current
CONTRACT SUM (APPROXIMATELY)
-