Call Us: +65 6383 4925
project
Contract 2001 Advance Earthwork for construction of Station, Tunnels, and CIQ Building for Rapid Transit System Link
DEVELOPER / MAIN CONTRACTOR
LTA /
Chuan Lim Construction Pte Ltd
COMMENCEMENT DATE / COMPLETION DATE
September 2017 – October 2018
CONTRACT SUM (APPROXIMATELY)
-
project
Contract 2001 Advance Earthwork for construction of Station, Tunnels, and CIQ Building for Rapid Transit System Link
DEVELOPER / MAIN CONTRACTOR
- Oxley Serangoon Pte Ltd
- L.S Construction Pte Ltd
LTA /
Chuan Lim Construction Pte Ltd
COMMENCEMENT DATE / COMPLETION DATE
September 2017 – October 2018
CONTRACT SUM (APPROXIMATELY)
-
project
Contract 2001 Advance Earthwork for construction of Station, Tunnels, and CIQ Building for Rapid Transit System Link
DEVELOPER / MAIN CONTRACTOR
- Oxley Serangoon Pte Ltd
- L.S Construction Pte Ltd
LTA /
Chuan Lim Construction Pte Ltd
COMMENCEMENT DATE / COMPLETION DATE
September 2017 – October 2018
CONTRACT SUM (APPROXIMATELY)
-
project
Contract 2001 Advance Earthwork for construction of Station, Tunnels, and CIQ Building for Rapid Transit System Link
DEVELOPER / MAIN CONTRACTOR
LTA /
Chuan Lim Construction Pte Ltd
COMMENCEMENT DATE / COMPLETION DATE
September 2017 – October 2018
CONTRACT SUM (APPROXIMATELY)
-
project
Contract 2001 Advance Earthwork for construction of Station, Tunnels, and CIQ Building for Rapid Transit System Link
DEVELOPER / MAIN CONTRACTOR
LTA /
Chuan Lim Construction Pte Ltd
COMMENCEMENT DATE / COMPLETION DATE
September 2017 – October 2018
CONTRACT SUM (APPROXIMATELY)
-
project
Contract 2001 Advance Earthwork for construction of Station, Tunnels, and CIQ Building for Rapid Transit System Link
DEVELOPER / MAIN CONTRACTOR
LTA /
Chuan Lim Construction Pte Ltd
COMMENCEMENT DATE / COMPLETION DATE
September 2017 – October 2018
CONTRACT SUM (APPROXIMATELY)
-
project
Contract 2001 Advance Earthwork for construction of Station, Tunnels, and CIQ Building for Rapid Transit System Link
DEVELOPER / MAIN CONTRACTOR
LTA /
Chuan Lim Construction Pte Ltd
COMMENCEMENT DATE / COMPLETION DATE
September 2017 – October 2018
CONTRACT SUM (APPROXIMATELY)
-
project
Contract 2001 Advance Earthwork for construction of Station, Tunnels, and CIQ Building for Rapid Transit System Link
DEVELOPER / MAIN CONTRACTOR
- Oxley Serangoon Pte Ltd
- L.S Construction Pte Ltd
LTA /
Chuan Lim Construction Pte Ltd
COMMENCEMENT DATE / COMPLETION DATE
September 2017 – October 2018
CONTRACT SUM (APPROXIMATELY)
-
project
Contract 2001 Advance Earthwork for construction of Station, Tunnels, and CIQ Building for Rapid Transit System Link
DEVELOPER / MAIN CONTRACTOR
LTA /
Chuan Lim Construction Pte Ltd
COMMENCEMENT DATE / COMPLETION DATE
September 2017 – October 2018
CONTRACT SUM (APPROXIMATELY)
-